Schedule of Condition reports: what contractors need to know

Schedule of Condition reports are often treated as a “surveyors’ document” that sits in the background. In reality, they can have a direct impact on how smoothly your project runs, how quickly concerns are resolved, and whether minor issues escalate into costly delays. For contractors, understanding what a Schedule of Condition is—and how to work with it properly—can protect your programme, your client relationship, and your reputation.

This article explains what contractors need to know: what Schedule of Condition reports are for, when they matter most, how they interact with site operations, and what best practice looks like on live projects.


1) What a Schedule of Condition report is (in contractor terms)

A Schedule of Condition report is a baseline record of the adjoining property’s condition (and sometimes parts of the client’s property) at a particular date. It typically includes:

  • structured written descriptions of rooms and elevations, and
  • a detailed photographic record, cross-referenced to the descriptions.

The report doesn’t “approve” your work or your methods. Its role is to document pre-existing defects so that if cracking, staining, or damage is alleged later, everyone has an evidence base to assess what has changed.

Why contractors should care

Because the moment a neighbour reports a crack, your job can be disrupted. A robust baseline record helps keep discussions factual and prevents your programme being derailed by uncertainty.


2) Why Schedule of Condition reports matter on real sites

A) They reduce unplanned stoppages and disruption

Where there is no baseline record, neighbours’ concerns often trigger:

  • urgent call-outs,
  • requests to pause works,
  • repeated visits by professionals,
  • escalating correspondence.

Even if your workmanship is excellent, the lack of an evidence record can cause friction. A good schedule helps issues get assessed quickly and objectively.

B) They protect your client—and by extension, your contract

Neighbour disputes often become client disputes. If your client faces allegations they can’t answer, they may push pressure down onto you (even unfairly) to “fix it” or stop.

When a Schedule of Condition exists, the client has a defensible position and the problem stays manageable.

C) They support fair, proportionate outcomes

Not every crack is caused by current works. Older properties often have historic settlement, thermal cracking, and cosmetic defects. A baseline record helps separate:

  • pre-existing condition,
  • normal wear and tear,
  • and genuine change potentially associated with the works.

That fairness keeps projects moving.


3) When contractors are most affected by Schedule of Condition issues

Certain stages trigger most neighbour concerns. Contractors should assume a Schedule of Condition will be relevant when the programme includes:

  • excavation close to neighbouring structures
  • demolition or breaking out
  • structural alterations introducing vibration
  • underpinning or basement works
  • piling and heavy plant
  • cutting chases or pockets near party/boundary lines
  • scaffolding erection close to external finishes
  • temporary weathering or roof opening works

If your job has any of these elements, a robust Schedule of Condition and a clear communication plan are essential.


4) What contractors should expect from a good Schedule of Condition report

A high-quality report should be:

A) Clear and navigable

Organised by:

  • external elevations, then
  • internal rooms in sequence,
    with consistent headings and referenced photographs.

B) Specific about defects

Not “minor cracking,” but:

  • where the defect is,
  • how extensive it is,
  • and what it looks like.

C) Evidential photography

Photos should be:

  • sharp and well lit,
  • labelled and referenced to the written notes,
  • including context and close-ups.

D) Transparent about limitations

If areas weren’t accessible, the report should say so clearly.

As a contractor, you don’t need to review every page—but you should understand the report exists, what it covers, and what the baseline is for the areas closest to your work.


5) Contractor best practice: how to work with the report on site

A) Ask to see it before higher-risk works begin

You don’t need it for everyday activities, but you should request sight of the schedule before:

  • excavation,
  • demolition,
  • structural steel installation,
  • underpinning,
  • major cutting into shared elements,
  • scaffold placements that rely on neighbour tolerance.

This allows you to be aware of existing defects and areas that need extra care.

B) Brief your site team

The best projects treat neighbour protection like a method statement item:

  • identify sensitive areas (chimney breasts, finished walls, tiled bathrooms adjacent to the works),
  • emphasise vibration management and sequencing,
  • remind teams about working hours and conduct near boundaries.

C) Align your method statements and protection measures

If the baseline record shows fragile finishes or existing cracking, consider:

  • dust and vibration controls,
  • temporary supports and protection,
  • careful breakout sequencing,
  • avoiding unnecessary percussive work near sensitive zones.

A schedule doesn’t change how you build—but it helps you predict where concern will arise.


6) What to do if the neighbour reports damage mid-project

This is where contractor behaviour matters most.

Step 1: Treat it seriously and keep it calm

Avoid dismissive statements like “that was there before” unless you’ve actually checked the schedule.

Step 2: Inform your client/PM immediately

Damage issues should be managed through the correct channel quickly.

Step 3: Compare against the Schedule of Condition

A professional comparison can confirm:

  • whether it’s pre-existing,
  • whether it’s new,
  • and whether it appears to be worsening.

Step 4: Protect and stabilise the situation

Even if the cause is uncertain, it may be appropriate to:

  • adjust sequencing,
  • add protective measures,
  • increase monitoring,
  • or reduce vibration exposure temporarily.

Step 5: Keep records

Maintain:

  • daily logs,
  • photos of the area,
  • plant used and operations occurring when the issue arose,
  • weather exposure notes if roofs/external areas are involved.

Good records protect everyone and speed up resolution.


7) Post-work check-off: why contractors should support it

A post-work check-off inspection:

  • confirms whether anything has changed,
  • provides closure,
  • and allows any genuine making-good to be programmed efficiently.

Contractors benefit because it:

  • reduces late-stage disputes,
  • helps retention and sign-off progress smoothly,
  • prevents “last-minute claims” after demobilisation.

8) Common contractor mistakes (and how to avoid them)

Mistake: relying on phone photos taken by the contractor

This is rarely seen as independent or structured enough.

Mistake: ignoring external features

Damage allegations often involve patios, garden walls, render, and boundary features—especially around excavation and access.

Mistake: dismissing concerns

Even if the allegation is incorrect, dismissive behaviour escalates the situation.

Mistake: failing to coordinate access and protection

If you need temporary access or protection measures near boundaries, agree it clearly and keep it tidy, secure, and professional.


9) Contractor checklist: practical actions that help

  • Confirm a Schedule of Condition exists before high-risk stages
  • Ask for the key pages for the nearest affected areas
  • Brief operatives on vibration/dust control and boundary conduct
  • Maintain clean, safe access routes and protect neighbour-facing finishes
  • Record key stages with dated site photos
  • Escalate concerns quickly and professionally
  • Support a post-work check-off and making-good programme